[ARCHIVED] Range Road 11 (Norris Beach Road)

Road Construction Update - RR 11

Work on Range Road 11 North (Norris Beach Road) will begin on July 10, 2021. Work includes grade, base & pave of 1.18 kms of Range Road 11 North of the Village at Pigeon Lake and a bridge replacement. 

Construction Schedule & Hours of Work

 All work performed on site will be during daylight hours. In the event crews fall behind schedule, a night shift may be introduced to return the project to the intended timeline to complete. Regular working hours will be 7:00 a.m. to 7:00 p.m., 7 days a week, weather permitting. 

No work at the Junction of Highway 13 or Crystal Springs Drive will be undertaken during hours of darkness. 

Tentative Construction Schedule:

Erect Pre-Construction Signage  
June 10, 2021
MobilizationJuly 5-10, 2021
Bulk Grading and DrainageJuly 10- 26, 2021
Bridge File 7312July 17-27, 2021
Granular Base CourseJuly 27 - August 1, 2021
Asphalt Concrete PavementAugust 1-8, 2021
Final Trimming & Clean-upJuly 31 - August 12, 2021
DemobilizationAugust 12-15, 2021


Detours 
A localized detour is intended for this project to provide a route around the construction zone to provide access to Crystal Springs and the south shore of Pigeon Lake throughout the construction period and specifically during the road closure for the installation of Bridge File 7312 at km 0.82. The roadway will be closed from just North of 6th Street to just South of Crystal Key Drive. Residents of Crystal Key and Crystal Springs will be required to use the Range Road 12 detour. Residents of Norris Beach will have access along Range Road 11. It is important to note the Crow Enterprises will ensure that local residents and businesses have access to their properties at all times. 