How long does the subdivision process take?

Generally, a subdivision takes approximately 3 to 6 months to complete. Some of the mandated timelines include:  

  • Deeming an application complete – 20 days 
  • Referrals to agencies & adjacent landowners – 21 days 
  • Review of complete subdivision application to condition approval – 30 days 
  • Appeal period – 21 days 

Fulfilment of subdivision conditions – subdivision approvals are valid for 1 year. All conditions of a subdivision must be completed within that year. Extensions for an additional year may be granted but the request and fee must be submitted before the file expires.  