Update: August 4, 2022
The 10 foot mower has completed mowing in Alder Flats, Buck Lake, Winfield, The Village at Pigeon Lake and is currently mowing in Mulhurst Bay. It has also completed all Subdivision west of The Village at Pigeon Lake. Both the Contract Mower and County Staff 15 foot mower have started mowing Range Roads and Township Roads.
Original Post:
The Roadside Mowing Program will start mid to end of this week with County Staff mowing all roads east of Secondary Highway 795.
The Contract Mower will be starting this week as well. They will be mowing all roads west of Sec. Hwy 795 and will be starting there and working their way west (last year they started in Winfield).
The 10 foot mower has completed mowing in the Buck Lake and Alder Flats area and is currently mowing in the Winfield area working his way east.