Project Update: June 29, 2022
Work has begun; should be done by mid-September (weather dependent).
Original Post:
This project is to upgrade the road (for approx. 3.2 km south of Hwy 13) which includes excavation and removal of poor subgrade material, improvements to vertical alignment, drainage improvements and clearing of County right-of-way.
The County is endeavoring to safely maintain local traffic access on this road during the project. Please be patient during the upgrades. Reduced speeds will be enforced. Thank you for your patience as the County strives to provide road infrastructure that allows for the safe travel of the public.
Should you require any further information on this project or any other project, please call the Public Works Call Centre at 780-361-6241 or email.