Work is scheduled to begin on Monday, May 17, 2021. Work will start at Hwy 613 and move south and west on the G3 road (subgrade prep followed by base course). Then crews will pave back the opposite direction coming from Hwy 2a, east to RR 240 and north to Hwy 613. This work will take 6-7 weeks to complete (weather dependent). We thank those in advance for their patience, care and attention when driving through the work zones. Safety is a high priority during construction with the end objective being a significant enhancement to the local road infrastructure.