Update: August 19, 2022
Work on RR 235 has begun and is approximately 50% done. Expect another 15 days to complete the work (RR 234 & RR 234), weather permitting.
Update: August 5, 2022
The work will begin on Range Road 235 on Monday, August 8, 2022; to be completed in two weeks (weather permitting). After completion of Range Road 235, construction will then move to Range Road 234. Roads will remain open for travel.
Original Post:
This project is a shoulder pull on Range Road 234 (6.4 km) and Range Road 235 (6.4 km) between Township Road 454 and Highway 613. Central Construction Group Ltd. has been contracted to complete this work. Work involved includes shoulder pull, spot road repairs and gravelling.
The County is endeavoring to safely maintain local traffic access on this road during the project. Please be patient during the upgrades. Reduced speeds will be enforced. Thank you for your patience as the County strives to provide road infrastructure that allows for the safe travel of the public.
Should you require any further information on this project or any other project, please call the Public Works Call Centre at 780-361-6241 or email.